Gaston County Landfill Gas Destruction Project
Protocol used to estimate reductions: Landfill Project Protocol, Version 5.0
Location of project site: Dallas, NC, USA
Project timeline: Current crediting period from 2008 – 2028
Project start date: November 18, 2008
Date and quantities of emission reductions:
29,173 mtCO2e (August 1, 2009 – December 31, 2009)
78,975 mtCO2e (January 1, 2010 – December 31, 2010)
67,184 mtCO2e (January 1, 2011 – December 31, 2011)
104,981 mtCO2e (January 1, 2012 – March 31, 2013)
79,889 mtCO2e (April 1, 2013 – March 31, 2014)
76,866 mtCO2e (April 1, 2014 – March 31, 2015)
75,452 mtCO2e (April 1, 2015 – March 31, 2016)
100,031 mtCO2e (April 1, 2016 – March 31, 2017)
122,699 mtCO2e (April 1, 2017 – March 31, 2018)
204,479 mtCO2e (April 1, 2018 – December 31, 2019)
110,704 mtCO2e (January 1, 2020 – December 31, 2020)
100,693 mtCO2e (January 1, 2021 – December 31, 2021)
115,191 mtCO2e (January 1, 2022 – December 31, 2022)
Type of project: Landfill Gas Capture/Combustion (carbon removal)
Legal or NGO standard: Climate Action Reserve
Project durability period: Permanent
Independent or 3rd party validation/verification: Ruby Canyon Environmental, LLC
Annual emissions reductions/removal: 115,191 mtCO2e (January 1 – December 31, 2022) *
* This represents the most recent verified annual emissions reduction, taken from the project verification report, dated July 6, 2022
Details of “accountability measures” if reversal or shortfall:
Enterprise Mobility carbon offset credits are paid for by rental customers who opt-in to the carbon offset program, and these purchases are matched by the Enterprise Mobility Foundation. The carbon offset credits are for emission reductions that have already occurred and been validated by an independent third-party review. If purchased credits are reversed, they will be replaced by Terrapass with credits of comparable quality.
The pertinent data and calculation methods needed to independently reproduce and verify the number of emission reduction credits issued using the protocol may be found in Section 3.0 of the Project Verification Plan, which is publicly available at Gaston County Landfill Gas Destruction Project | Terrapass.